How it works

How we manage your utility applications, step by step

From your first enquiry to the day the supplies go live. Here is what happens at each stage, how long it typically takes, what we need from you and what you pay to whom.

The short version

We run the applications. The operators build the connections.

Every utility connection in Great Britain goes through the company that owns the network: the electricity network operator, the gas network, the water and sewerage company, and a broadband network such as Openreach. Much of the physical work can also be done by accredited independent contractors.

Our job is everything around that work. We find out who covers your site, work out what you need, prepare and submit the applications, get competing offers where the rules allow, check each one and coordinate the dates with your build. The process is the same whether you are building one house or two hundred. The detail and the number of operators change.

Who we work with

We cover England, Wales and Scotland.

The full process

Eight stages from enquiry to live supplies

The badges show typical timings that operators publish. They are a guide, not a promise, and they vary by operator and by site.

What makes it take longer

New substations, network reinforcement, long mains, wayleaves over third-party land and road permits all add time. Thames Water, for example, says planning a service connection date can take up to three months because of permits. We give you a realistic programme once we know the site.

Want a quick view for your project? Try our connection planner, or read how long a new connection takes.

  1. 1Ideally once you have a site layout

    You tell us about the site

    Send the address, plans and what you are building through our quote form. Rough details are fine at this stage.

  2. 2Before you commit to anything

    We confirm the route and quote our fee

    We identify the operators that cover your site, the applications you need and any early risks to cost or timing. Then we send a fixed quote for managing it.

  3. 3Electricity budget estimates: 10 to 20 working days

    Early checks, where they help

    On larger or uncertain sites we ask for budget estimates, which are indicative and not binding, and pre-development enquiries to the water company about capacity.

  4. 4Once drawings and loads are agreed

    Applications prepared and submitted

    We prepare each application with the drawings, loads, meter positions and dates in the format each operator asks for, and send them in together.

  5. 5Electricity quotes: 5 to 65 working days, by size

    Offers come in

    Electricity quote times are set by national standards. Gas quotes take 4 to 21 working days depending on the load. Bristol Water, for example, aims to quote a service connection within 28 days. Independent offers are requested at the same time.

  6. 6Electricity offers often valid for 90 days

    We check, compare and you accept

    We check each offer for scope, exclusions and timing, compare alternatives like for like and explain our recommendation. You accept and pay the operator you choose.

  7. 7About 8 weeks from payment for 1 to 4 homes (NGED)

    Works planned and built

    We agree dates and tell your builder what groundwork to do. Under the gas networks' standards, start and finish dates are offered within 17 days of acceptance, and Cadent says its works typically take 6 to 8 weeks from payment.

  8. 8Water: within 21 days of inspection and payment (Bristol Water)

    Connections, meters and handover

    The operators make the final connections. We remind you to book an energy supplier for the meters and broadband for occupation, and confirm every supply is live.

What we need from you

Information to have ready

Send what you have. We'll tell you what's missing and help you put the rest together.

  • Site address, postcode and a location plan with the site edged in red
  • Planning permission and the approved drawings
  • Site layout, with plot numbers on developments
  • Number and type of homes or units
  • Heating type, plus any EV chargers, solar panels or batteries
  • Preferred meter positions
  • Drainage layout, if you are connecting to a public sewer
  • Details of any existing supplies or utility records
  • When you need each supply, and any phasing
  • A signed letter of authority, so we can apply for you
See the full application checklist
Who is the applicant

You stay the customer, we act for you

In most cases the connection offers are made out to you, or your company, as the owner or developer. A letter of authority lets us deal with the operators on your behalf: submitting applications, answering their questions and agreeing dates.

That means you keep a direct contract with each operator, and you can see exactly what each one charges. If you have already started an application, send us what you have and we'll pick it up from there.

Already have a quote?

We can check an offer you already hold before you accept it, and tell you whether it's worth asking for an alternative.

Clear boundaries

What we do, and what we don't

We manage applications. We don't install anything, so our advice isn't tied to selling you our own work.

We do

  • Confirm which operators cover your site and what each one needs
  • Work out loads and supply sizes with you
  • Prepare and submit complete applications
  • Ask for independent offers where the work is contestable
  • Check every offer for scope, exclusions, timing and cost
  • Handle queries, acceptance paperwork and dates
  • Tell your builder what groundwork to do, and when
  • Chase each operator until the supplies are live

We don't

  • Dig trenches, lay cables or pipes, or make connections
  • Supply energy or fit meters (your supplier does that)
  • Design off-mains drainage such as treatment plants
  • Set operator prices, capacity or connection dates
  • Guarantee what an operator will offer or when
  • Work in Northern Ireland

Network capacity, prices and dates are set by the operators. What we can do is make sure your applications are complete, on time and followed through.

Fees and charges

How our fee works, and what you pay the operators

There are two kinds of cost: our fee for managing the applications, and the operators' own charges for the connections.

Our fee

  • Quotes are free and no-obligation. Tell us about the site and we'll send a quote for managing it.
  • Agreed and fixed before we start. You know exactly what our fee is before any work begins.
  • Clear scope. Our quote lists the utilities and applications it covers, so you know what's included.

What you pay the operators directly

The connection charges are set by each operator and paid to them. Some are payable even before you accept an offer, so we tell you about them up front.

ChargePaid toGood to know
Electricity connectionDNO, IDNO or ICPNGED's published guide shows about £2,500 + VAT for one home (indicative, NGED areas only).
Assessment and design feeElectricity network operatorCharged for preparing an offer, whether or not you accept it. When it is charged varies by operator.
Gas connectionGas network or UIPQuoted case by case. Cadent asks for offers to be accepted and paid within 90 days.
Water connection and infrastructure chargesWater company or self-lay providerPublished each year by each company. Affinity Water's 2026/27 infrastructure charge, for example, is £615.
Pre-development enquiryWater companyOptional, but encouraged on larger sites. Anglian Water's 2025/26 fee is £741 for water and wastewater.
Sewer connection and adoptionSewerage companyFees for Section 106 connections and Section 104 adoption are in each company's charging arrangements.
BroadbandOpenreach or another networkOpenreach full fibre is free on sites of 20 or more premises. Smaller sites pay a contribution.
Meters and energyYour energy supplierThe supplier fits the meter and bills you for the energy you use.

Your builder's groundworks, such as trenches and ducts on your own land, are usually a separate cost. Read our connection costs guide.

Questions about how we work

How much do you charge?

Our fee depends on the site and the number of utilities, and it is agreed and fixed before we start. Our quote is free and there is no obligation to go ahead.

Do you do the connection work?

No. The network operators, water companies and accredited independent providers do the physical work. We manage the applications and the process, so we can compare their offers rather than sell you our own.

Who pays the network operators?

You do, directly. The offers are usually made out to you as the owner or developer, so you see exactly what each operator charges.

How long does the whole process take?

For a simple supply, often a few months from a complete application. Larger sites, new substations or road works take longer. We give you a realistic programme once we know the site.

Can you take over an application I have already started?

Yes. Send us what you have so far and a letter of authority, and we will pick it up from where it is.

What is a letter of authority?

A short signed letter that lets us deal with the network operators and water company on your behalf. Operators ask for one when an agent applies for the owner.

Do you cover the whole of the UK?

We cover England, Wales and Scotland. We don't handle applications in Northern Ireland.